The Work Isn’t Slow. The Waiting Is.


Workflow diagram, product brief, and user goals are shown

Pick any feature currently moving through your team and track it honestly from the moment work started to the moment it shipped. Then add up only the hours someone was actively building, testing, or designing it. For most teams that number lands shockingly low. David J. Anderson, who created the Kanban method, puts typical flow efficiency in the range of 1 to 25 percent, with most cases sitting near the bottom of that band. The first Kanban system he measured in 2004 started at 8 percent.

Read that the other way around. If a work item is actively worked 15 percent of the time, it is sitting idle the other 85 percent. It is waiting: for a review, for a dependency, for a decision, for a person who is busy finishing something they started three weeks ago. The build was never the bottleneck. The waiting was. And the thing that creates most of that waiting is the one move that feels most like progress: starting more work.

Flow efficiency is the number nobody on your team is looking at

Flow efficiency is a simple ratio. Take the time a work item spent actively being worked, divide it by the total elapsed time from start to finish, and multiply by a hundred. A feature that took four weeks to ship but only involved five working days of actual effort has a flow efficiency around 25 percent, and that would be a good result by Anderson’s benchmarks. The corollary he draws from the field data is blunt: for most work items, between 75 and 99 percent of their duration is pure waiting time, and that waiting is non-deterministic, meaning you cannot predict or schedule it.

The reason this number stays invisible is that nobody is incentivized to measure it. Engineers report story points. Managers report velocity. Executives ask when it ships. None of those instruments can see the queues between the active steps, and the queues are where the time goes. A team can look fully utilized, every person busy every hour, and still move work through at a crawl, because being busy and being in flow are not the same state. Busy usually means everyone is working on their own thing. Flow means the work is moving.

I wrote recently about how velocity can climb while nothing actually ships faster. Low flow efficiency is the mechanism underneath that paradox. You are optimizing for people being occupied when you should be optimizing for work being finished.

The counterintuitive lever: start less, finish sooner

Here is the part that takes a while to believe, because it runs against every instinct a busy team has. The fastest way to get more things done is to have fewer things in progress at once.

This is not a motivational slogan. It is arithmetic. It comes from Little’s Law, a result from queuing theory that applies directly to any flow of work: average work in progress equals throughput multiplied by average cycle time. Rearrange it and you get the version that matters for delivery:

Average cycle time = work in progress ÷ throughput.

Throughput is how much your team actually completes per unit of time, and it is largely fixed in the short run by your team’s real capacity. Work in progress is how many things are open at once, and that number is almost entirely a choice. Because the relationship is linear, that choice controls cycle time directly.

Walk through it with round numbers. Say your team genuinely finishes five work items in an average week. That is your throughput, and no amount of pressure changes it this quarter. Now suppose fifteen items are open at any given time, which is normal for a team that says yes to everything. Cycle time is 15 ÷ 5, so each item takes about three weeks from start to done. Cut the open items to five, change literally nothing else about the team or the work, and cycle time becomes 5 ÷ 5, one week. The same team, the same people, the same capacity, now delivers any given feature three times faster, purely because fewer things are competing for attention at once.

This is why the Kanban practice of setting work-in-progress limits exists, and why practitioners repeat the phrase “stop starting, start finishing.” Teams that cap how much is open at once routinely cut their cycle times without adding a single person. You are not working harder. You are letting work finish before you pile more on top of it.

Why starting more feels like progress and produces the opposite

If the math is this clean, why does every team default to the broken version? Because starting something is visible and finishing something is slow, so a backlog of started work feels like momentum even as it strangles throughput.

Every item you start but do not finish becomes a standing tax on everything else. The clearest number on this comes from the cost of context switching. The American Psychological Association, summarizing research from psychologist David Meyer, notes that the mental switching between tasks can cost as much as 40 percent of someone’s productive time when the switching is frequent. That is an upper bound rather than a daily average, but the direction is not in dispute: every extra project a person is asked to hold at once skims capacity off all the others. Two open work streams already cost real overhead; by the third or fourth, a meaningful slice of the day is going to the switching itself. That is the tax, and every unfinished item you are juggling keeps charging it.

Stack those two forces together and the trap is obvious. High work in progress lengthens cycle time through Little’s Law, and it simultaneously shreds the capacity that produces throughput in the first place. The more you start, the slower each thing goes, and the slower each thing goes, the more tempting it is to start something else while you wait. It is a doom loop that looks and feels exactly like diligence.

The quarter I watched a frozen intake speed everything up

I spent more than two decades in IT operations at a large telecom, and the most useful thing I ever did for delivery was also the thing that felt most like doing nothing. We hit a stretch where leadership, acting in good faith, kept green-lighting initiatives faster than we could close them. At the low point my group had something like eleven active projects running against a team that could realistically carry three or four at a time. Every status meeting was a tour of things that were almost done. Nothing was actually done.

I stopped starting. We froze new intake, listed everything in flight, and made a rule that nothing new began until something shipped. The pushback was immediate, because from the outside it looked like we had chosen to go slower. What actually happened is that the half-built work started crossing the finish line, one item at a time, and within two months we were completing more per month than we had when we were “working on” three times as much. We had not added a single person. We had just stopped forcing the team to pay the switching tax on eleven fronts at once.

The same pattern shows up in miniature in the fractional operations work I do now for smaller companies. A founder will tell me the team is slow and ask about hiring. Then we count open work streams and find a five-person team juggling fourteen. The problem was never speed. It was that nobody had ever told the team it was allowed to finish one thing before touching the next.

Smaller batches are the other half of the same idea

Limiting how much is in flight is one lever. Shrinking the size of each thing is the other, and they reinforce each other. A large release is simply a giant batch of work that cannot finish until every part of it is ready, so it sits in the queue inflating cycle time for everything behind it. I argued the risk side of this in why the big release is the most dangerous way to ship; the flow side is just as strong.

The DORA research program, the longest-running study of software delivery performance, treats working in small batches as a core capability that predicts both delivery and organizational performance. Its guidance is concrete: a unit of work should be completable in hours to a couple of days, and anything that will take more than a week should be decomposed before development starts. Smaller batches get feedback faster, make each change easier to understand, and counterintuitively reduce risk, because a small change that breaks is a small thing to diagnose and reverse.

This has a sharp edge in 2026. DORA’s recent work finds that working in small batches is what turns AI-assisted speed into actual value rather than instability. I covered the darker version of that story in how AI made teams faster while their delivery data got worse. If your team is generating code faster than ever but pushing it through the same bloated batches and overloaded pipeline, you are just filling the queues quicker. The waiting still eats the gains.

What to actually change on Monday

You do not need a tooling migration or a new methodology to act on this. You need to make waiting visible and then stop feeding it.

Start by measuring one real cycle time. Take five recently shipped items, find when work genuinely started and when it genuinely shipped, and estimate how many of those calendar days involved active work. The ratio will be uncomfortable, and that discomfort is the point. It is the first time most teams see their flow efficiency at all.

Then cap work in progress somewhere below what feels comfortable. If your team has five people and ten things open, the number is too high; try limiting active items to roughly the number of people, or fewer. Expect it to feel wrong for about two weeks while the started-but-unfinished pile drains. Hold the line, because that drain is exactly the throughput you were missing.

Finally, attack batch size directly. Before anything enters development, ask whether it can ship in under a week, and if it cannot, split it until it can. The goal is not smaller ambitions. It is a steady flow of finished work instead of a warehouse of work that is almost done.

The uncomfortable truth in the flow-efficiency numbers is that most teams do not have a speed problem. They have a waiting problem that they keep making worse every time they start one more thing to look productive. The work was never slow. Give it room to finish, and it moves.

Ty Sutherland

Ty Sutherland is the editor of Product Management Resources. With a quarter-century of product expertise under his belt, Ty is a seasoned veteran in the world of product management. A dedicated student of lean principles, he is driven by the ambition to transform organizations into Exponential Organizations (ExO) with a massive transformative purpose. Ty's passion isn't just limited to theory; he's an avid experimenter, always eager to try out a myriad of products and services. While he has a soft spot for tools that enhance the lives of product managers, his curiosity knows no bounds. If you're ever looking for him online, there's a good chance he's scouring his favorite site, Product Hunt, for the next big thing. Join Ty as he navigates the ever-evolving product landscape, sharing insights, reviews, and invaluable lessons from his vast experience.